Bsalim - Centre Bsalim 394 - Lebanon

Welcome to The Eid Law
50 YEARS

OF EXPERIENCE

We are Lebanese Lawyers firm practice in personal injury, family, criminal, divorce, corporate, legal assistant and labor litigation, with an emphasis on complex contractual matters and mass tort litigation. We are a leading group of highly professional lawyers whose goal is to protect you, your family and business. We aim to assure our clients that with our help it is possible to quickly and effectively resolve any issue. 

Our services

Business Law
The EID Law Firm is a Lebanese Business Law, Contracts and Commercial law firm that represents clients in various legal matters
Criminal Law
We choose unique and the most effective course of action for each case, both by leading the proceedings and by obtaining and submitting proofs
Civil Law
We belong to the market leaders when it comes to provide legal services to citizens, companies, local authorities and governmental agencies

Our Practice Areas

Eid law Firm Practice Area



Banking & Financial Law

We have significantly participated in foundation and subsequent activity of investment funds, investment companies and unit funds .

This activity has included drafting the necessary contracts, agreements and other legal documents as well as co-operation and assistance.

We gained extensive experience not only in the area of financial law, but also in the area of banking law, because the co-founder of this firm EDY EID Holder a law degree And holder a Master Degree in Jurist Affairs And holder a Master Degree in Banks and Stock Market  Operations of international Banks (Comparison on Legal and Practical-Executive status)

 

Free Consultation

    Business Law, Commercial Agreements

    The EID Law Firm is a Lebanese Business Law, Contracts and Commercial law firm that represents clients in various legal matters involving Business Law, including drafting and negotiating diverse agreements which arise in commercial transactions and business relationships, such as contracts with customers, vendors and other suppliers, joint venture agreements, employment contracts, independent contractor agreements, construction contracts, renovation contracts, and other commercial agreements, as well as the purchase or sale of a business.

    ______________________________________________________________________

    Quality Legal Services for Contracts, Commercial Law

    We believe that our clients are best served through a practical and business-oriented application of our diverse skills. Our business law enables us to focus quickly on the legal and economic issues.

    Our firm seeks to not only analyze and resolve legal issues, but also to assist each client in achieving their immediate and long-term goals. At the core of the firm’s practice is the negotiation and drafting of commercial agreements, and representing businesses and individuals in business transactions, and commercial relationships.

    ______________________________________________________________________

    Personal Service and Commitment to Clients

    Our clients can expect the EID Law Firm to be responsive and genuinely interested in each client’s legal matters. Our Lawyers communicates with our clients on a regular basis. Telephone calls are answered promptly, and ample time is devoted to each client. We believe that our future is linked to the success of our clients. The firm is committed to continually strive for excellence in both legal services and client relations.

    The Importance of Clearly Drafted Contracts

    In the course of operating a business, and even in one’s personal life, we enter into many types of contracts and written agreements. Written agreements are important, especially for businesses, since reliable sources of products, parts, equipment, labor and services are essential for a successful business.

    If you sign any contract, even a “standard contract” or proposal without competent legal representation, you may be positioning yourself at a distinct disadvantage. If the other party’s attorney prepared the contract, that lawyer probably drafted the contract for the sole purpose of protecting his or her client’s interests. In that situation, it is vitally important that your attorney protect your interests as well.

    Similarly, if the other party or even both parties together, prepared the contract without a lawyer, it may be vague, and might not properly express the parties’ intentions at all. Also, while the parties’ self drafted agreement might appear to be fair, it may lack important legal provisions, thereby rendering the entire agreement void and unenforceable. Alternatively, even if it is a legally binding, enforceable and fair contract, it may nevertheless be silent on certain key issues, thereby inviting litigation in the event of a dispute.

    ______________________________________________________________________

    Avoiding the Unfair Contract

    The purpose of a contract should not be to trap one party or the other. A proposed agreement that is a trap for the unwary should not be signed. Instead, it should re-negotiate and revised or redrafted, to create a fair and workable relationship. The EID Law Firm is proud of our Contracts and Commercial Lawyer’s thorough negotiation and meticulous drafting of many types of contracts.

    ______________________________________________________________________

    Our Lawyers Will Carefully Negotiate and Draft Your Contract

    The EID Law Firm negotiates and drafts contracts for various types of transactions, commercial relationships and business deals. Our Lawyers often anticipate many potential issues that might arise in the future, and attempt to address those issues in the contract. Once our clients have explained the substance of their oral agreement, and their expectations, we thoroughly negotiate, review and/or draft the contract, with the aim of safeguarding our client’s rights, and avoiding potential disputes. The advantage of hiring a lawyer experienced in contract negotiation and drafting cannot be overemphasized.

    We draft and negotiate many diverse agreements which arise in commercial transactions and business relationships, including:

    • Shareholders’ Agreements
    • Limited Liability Company Operating Agreements
    • Partnership Agreements
    • Stock Buy-outs (One Shareholder Purchasing another Shareholder’s Stock in a Corporation)
      •Contracts and Other Documents for the Purchase or Sale of Various Types of Businesses including Asset Sales and Stock Sales)
    • Employment Contracts
    • Independent Contractor Agreements
    • Confidentiality and Non-Compete Agreements/Non-Competition and Non-Disclosure Agreements (NCND) and (NNN)
    • Joint Venture Agreements
    • License Agreements
    • Business Management Agreements
    • Contracts with Customers, Vendors and Other Suppliers
    • Contracts for Construction and Home Renovation Projects
    Free Consultation

      Civil Law

      We belong to the market leaders when it comes to provide legal services to citizens, companies, local authorities and governmental agencies in the area of civil law.

      The services in this area are focused on Civil Law, Labor and Employment Law and Family Law.

      Based on the many years’ of experience in this field, we can provide our clients with a single advice or the complex solution of his or her problem.

      We draft legal documents of all kinds, including agreements settling disputable relations, always with the aim of finding the best solution for the client.

      Some lawyers are specialized in Real Estate Law.

      We are representing a number of real estate agencies, helping them prepare sales contracts and providing other necessary legal services. The variety of problems that arise from the wide mass of Civil Law makes us continuously increase our proficiency in this area

      Free Consultation

        Corporations Law

        For new businesses, we help our clients select the type of legal entity for their business. We can consult with the client’s accountant, in order to enable the client to determine which type of legal entity type best suits the client’s financial and tax plan for the business.

        As an experienced business law firm, we will make sure that your business is properly formed, in conformity with Lebanese laws.

        We represent international Corporations, Off-shore, Holding, Stock market, Limited liability, representative office on a variety of Lebanese business and corporate legal matters, including:

        • Drafting and Negotiating Business Contracts
        • Employment Agreements
        • Independent Contractor Agreements
        • Confidentiality Agreements (Non-Disclosure Agreements)
        • Non-competition and Non-solicitation Agreements
        • Commercial Lease Agreements
        • Purchase of a Building
        • Joint Venture Agreements
        • Purchase or Sale of a Business
        • Mergers and Acquisitions
        • Contract Disputes
        • Commercial Arbitration and Commercial Mediation of Disputes
        • Litigation
        • Collection
        • Dissolution and Liquidation of a Business
        Free Consultation

          Criminal Law

          We provide legal services in the area of Criminal Law,

          The legal services are provided both at pre-trial proceedings and at trials.

          We represent charged, accused or injured and involved parties.

          The legal assistance is provided also by means of consulting, also in relation to corporations.

          We choose unique and the most effective course of action for each case, both by leading the proceedings and by obtaining and submitting proofs.

          For this purpose, we cooperate with experts in related professions, such as court experts or other experts.

          We have a high rate of success in the area of alternative methods of resolving criminal conflicts.

          Free Consultation

            Real Estate Law

            The EID Law Firm represents its clients in diverse real estate matters. We take a personal approach to each of our client’s real estate transactions, and work closely with each client from beginning to end, in order to insure that each client’s financial and legal interests are properly protected. For most people, the sale or purchase of a home, whether a house, condominium or co-operative apartment is the largest financial transaction of a lifetime. Ralph EID is an experienced real estate attorney, handling the sale of condominiums, co-operative apartments and single and multi-family houses. As a Lebanese lawyer, Ralph EID is well versed in all aspects of real estate transactions, and is confident that you will appreciate his attention to detail and thoroughness, as well as his ability to assist you during all steps of this important transaction.

            Real Estate Transactions

            You can feel confident selecting the EID Law Firm as your Lebanese real estate lawyer for any of the following real estate matters:

            • Purchase and/or Sale of Residential Real Estate (Including Houses, Vacant Land, Condominiums and Co-ops)
            • Purchase and/or Sale of Commercial Real Estate
            • Leases and License Agreements for Residential and Commercial Real Estate
            • Mortgage Loan and Co-op Loan Refinancing
            • Real Estate Litigation
            • Transactions involving single and multi-family houses, condominiums, and co-ops
            • Sale of commercial real estate
            • Store leases, offices leases, and sub-leases of commercial real estate
            Free Consultation

              Frequently
              Asked Questions

              Starting a Business in Lebanon

              Below is a detailed summary of the bureaucratic and legal

              hurdles faced by entrepreneurs wishing to incorporate and register a new firm in Lebanon

               

              No.      Procedure                 

              1- Designate a Lebanese lawyer

              Agency: Lawyer

              Each newly formed company must retain and pay an attorney on an annual basis. On April 26 2012, the Beirut Bar Association increased the minimum annual retainer to LBP 9,000,000 effective as of January 2013. This retainer can be paid by the company during the year. Startup fees are set by the Beirut Bar Association at LBP 3,000,000.

               

              2- Deposit the capital in a bank

              Agency: Bank

              This procedure can be carried out on the basis of a signed and notarized copy of the articles of association.

               

              3- Register at the Company Registry

              Agency: Commercial Register

              The applicant submits the following documents to the company registrar at the Commercial Court, along with the total amount of required fees:

              • Articles of association
              • Commercial circulars
              • Minutes of the first general meeting of the partners
              • Registration application and a draft of the registration certificate to be issued
              • Document attesting the capital deposit
              • Partners’ identity cards or passports (copy)
              • Documents evidencing that the company is entitled to occupy the premises where it exercises its activities

               

              4- Notify the Ministry of Finance of commencement of business operations

              Agency: Ministry of Finance

              Within 2 months of registration, the company must submit a notification of commencement of business activities to the Ministry of Finance in order to register for income tax and VAT.

               

              5- Register at the National Social Security Fund (NSSF)

              Agency: National Social Security Fund

              This procedure has two functions: “Registration” of a new employee and “Confirmation” by the system.

               

              The “Registration” function entails submitting a file for each new employee at the NSSF regional office closest to the company premises and obtaining a file reference number (or a receipt acknowledging the registration) immediately upon the submission. Once this “Registration” function is completed, the business is considered to have fulfilled its legal obligations with the NSSF. The benefits to the newly registered employees, under NSSF rules, will also become immediately effective. The Time to complete this procedure is 1 day at no cost to the employer or the employee.

               

              The “Confirmation” function consists of issuing a hard copy document (printed on a special size sheet) in the name of the registered employee along with his/her unique NSSF ID. Due to the lack of printing equipment at NSSF, the confirmation documents are printed in batches every few days or so. Therefore, it could take up to 30 days for a confirmation sheet to be received by the newly registered employee.

               

              6- File internal labor regulations (règlement intérieur) with the Ministry of Labor

              Agency: Ministry of Labor

              When the number of employees at a company reaches 15 then the company will have to file internal labor regulations (règlement intérieur) with the Ministry of Labor according to Art. 66 of the Labor Code.

               

              7- Register for VAT

              Agency: VAT Department

              Registration for VAT is done at the VAT Department. To obtain a VAT certificate of registration, it may take between 7 and 10 days. There are specific forms to fill out for each kind of registration. The VAT department is independent from the taxes’ department. The registration in both departments is free of charge.

               

              8- Obtain a company seal

              Agency: Seal maker

              Although not mandated by law, the majority of companies prefer to have company stamps.

              They can be order at any seal-making company.

               

               

              Dealing with Construction Permits in Lebanon

              Below is a detailed summary of the procedures, time and costs to build a warehouse in Lebanon. This includes obtaining necessary licenses and permits, completing required notifications and inspections and obtaining utility connections.

              Measure of efficiency

              1- Obtain a recent planning certificate

              Agency: Directorate General of Urban Planning (DGU)

              BuildCo must submit a recent planning certificate (they are usually valid for 3 months) among the necessary documents to request a building permit.

              BuildCo must have a receipt from the municipality and should pay the value of the stamps for this procedure.

              1- Land certificate stating the dimension and the content of the land

              2- Cadastral plan showing the positioning of the land

              3- Receipt from the municipality of the planning certificate

              2- Obtain a topographic study

              Agency: Topographic engineer

              BuildCo needs to obtain a topographic study at the beginning of the construction in order to have accurate details about the levels and limitations of the land plot. This study is required for the construction permit application.

              3- Hire a technical auditor and obtain approval of drawings

              Agency: Technical Auditor

              Based on Decision No. 1/1192 dated November 23, 2012, companies must hire a technical auditor accredited by the government who must review and approve the drawings related to the project before the building permit can be issued. They may request that modifications be made to the drawings. Throughout the construction phase, the auditors must also ensure that construction works are duly performed. And upon completion of the works, they must attest that the construction work was carried out properly.

              4- Obtain approval of file by Order of Engineers (where engineer is registered) and pay duties to Order

              Agency: Beirut Order of Engineers

              The file must be submitted to the Order of Engineers if the engineer is registered (Beirut Order of Engineers or Tripoli Order of Engineers). The file should include the following:

              • A construction permit application signed by that same civil engineer or architect jointly with the real estate owner,
              • The design plans,
              • An agreement between the property owner and the architect or engineer responsible for the project described.

              In order to be submitted as part of the application for a building permit, the file must bear the seal and registration number of the relevant Order of Engineers. The Order of Engineers meets twice a week.

              A fee schedule for the permit to start construction works from the Order of Architects and Engineers has been implemented in Beirut since 2010:

              • 1 and 3,000 sq. m., the cost is de LBP 1,500.00 per sq. m.
              • 3,001 and 6,000 sq. m., the fee is LBP 3,000.00 per sq. m.
              • 6,001 and 9,000 sq. m., the fee is LBP 4,500.00 per sq. m.
              • Above 9,001sq. m., the fee is LBP 6,000.00 per sq. m.

              The cost is LBP 1,950,900.00.

               

              5- Submit building permit application to Urban Development Department

              Agency: Urban Development Department, Directorat Général d’Urbanisme (DGU)

              BuildCo must submit the file described in the previous procedure to the Urban Development Department. In Beirut and Tripoli, the file is referred to the municipal engineering departments. The process takes up to 6 months. The Urban Development Department is a subdivision of the Directorate General of Urbanism.

              6- Request and receive pre–approval inspection from Urban Development Department

              Agency: Urban Development Department, Directorat Général d’Urbanisme (DGU)

              The Urban Development Department inspects the property and the plans to ensure that they are consistent with the construction laws and regulations, and then issues its clearance for the issuance of the building permit and calculates the building permit taxes. The inspection itself is completed in a day, but it takes a while from the date BuildCo requests the inspection until the date the inspector arrives.

              7- Pay building permit taxes to the municipality

              Agency: Municipality

              The Urban Development Department refers the file to the relevant municipality (in the case of the city of Beirut, to the Administrator of the City of Beirut). The municipality collects the construction permit taxes and issues the construction permit in the name of the property owner. Payment is made at the municipality.

              According to Decree No. 60 of 1988 on Municipal Taxes, the building permit taxes paid to the Municipality are a certain value per square meter of the building. However, this value per square meter is calculated based on the value of 1 square meter of construction as follows:

              – From the value of LBP 1 – 25,000: 1.5% of the construction value of 1 square meter

              – value between LBP 25,000 – 100,000: 2% of the construction value of 1 square meter

              – Greater than LBP 100,000: 1% of the construction value of 1 square meter

              In the case of Doing Business, the value of 1 square meter of construction is the total construction value / 1,300.6 sq. m.

              Therefore, the value per square meter without taxes to be paid is calculated as follows: (1.5% * 25,000) + (2% * 75,000) + (1% * [total construction value – 100,000]).

              Then a 15% municipal tax is added to the value above + 0.05% of the construction value of 1 square meter to obtain the total value to be paid per sq. m. as a municipal contribution.

              A second tax of 12% of the value above must be paid per square meter as a national tax.

              A contribution of 5% of the value above must be paid per square meter to the Order of Engineers and Architects.

              Therefore, the above values would all be added to obtain the total cost per square meter paid to the municipality for all building permit fees, which is then multiplied by 1,300.6 sq. m. for the purposes of the Doing Business case study.

               

              8- Obtain building permit

              Agency: Municipality

              By law, construction work can start if no decision about the building permit application has been made 15 days after the submission date. In practice, however, this is not applied, and people wait 4 months on average.

               

              9- Obtain starting order permit from Order of Engineers

              Agency: Beirut Order of Engineers

              To start construction the engineer and/or architect must pay the dossier fee according to the number of professionals involved in the construction work (civil engineer, mechanic engineer, electrical engineer, geotechnical engineer, among others). The fee should not exceed LBP 200,000.00

               

              10- Submit permit from Order of Engineers to the police

              Agency: Police                      

               

              11- Request and receive inspection from the Ministry of Public Works for water and sewage

              Agency: Ministry of Public Works

              With follow-up, it takes 10 days from the time an inspection is requested until an inspection begins. Without follow-up, however, the inspection might never take place.

              12- Submit application and receive approval for an occupancy permit from the Order of Engineers

              Agency: Beirut Order of Engineers

              Following completion of construction, an application for approval of an occupancy permit must be submitted to the Order of Engineers. The Order must give a written and stamped approval first.

              13- Submit application and receive approval for an occupancy permit from the Directorate General of Urban Planning (DGU)

              Agency: Urban Development Department, Directorate General of Urban Planning (DGU)

              Once construction has been completed, an application for approval of an occupancy permit must be submitted to the Urban Development Department. The Urban Development Department performs an on-site inspection of the building to ensure that it is in compliance with the construction permit and approved plans.

              The application for an occupancy permit must be accompanied by the plans related to the completed construction, signed by the engineer in charge, and stamped by the Order of Engineers. Following the clearance from the Urban Development Department, the file is forwarded to the relevant municipality (in the case of Beirut, to the Administrator of the City of Beirut) that will issue the occupancy permit in the name of the property owner. According to the law, the occupancy permit must be issued within a month. However, this time limit is not enforced in practice.

               

              14- Receive on-site inspection from the Directorate General of Urban Planning (DGU)

              Agency: Urban Development Department, Directorate General of Urban Planning (DGU)

              It takes about a week to schedule the inspection.

              15- Obtain occupancy permit

              Agency: Urban Development Department, Directorate General of Urban Planning (DGU)

              By law, the time limit for the procedure is 30 days, but in practice, it takes much longer to obtain the occupancy permit — about 55 days with follow-up.

               

              16- Obtain water connection

              Agency: Water of Beirut and Mount Lebanon

              BuildCo must submit an application for water connection accompanied by various documents.

               

              17- Receive onsite inspection from the Ministry of Finance and obtain estimate of leasing value of the warehouse

              Agency: Ministry of Finance

              Once the occupancy permit is issued, an inspector from the Ministry of Finance visits the site to prepare an estimate of the leasing value of the warehouse. This estimate is necessary to register the building.

               

              18- Register the building with the Real Estate Registry

              Agency: Real Estate Registry

              According to Tables 1 and 2 attached to the Decree Law No. 148 dated 12/6/1959 and its amendments, the registration fees consist of: (i) 1% of the leasing value of the warehouse (ii) minor taxes such as topography tax (approximately LBP 250,000) and deed and contract taxes (approximately LBP 100,000). There is an additional Municipality tax (5% of the total taxes in the aforementioned costs above), provided in Article 90 of the Law of the Municipality Duties and Taxes No. 60/88 dated 12/8/1988 and its amendments.

              Getting Electricity in Lebanon

              Below is a detailed summary of the procedures required for a business to obtain an electricity connection for a newly constructed building in Lebanon.

              Procedure                 

              1- Obtain neighbor’s electricity bill (for address of closest building)

              Agency: Neighbor

              The customer needs to obtain an electricity bill from their neighbor or the identification number of the neighbor’s meter box (showing the address of the closest building. This is needed when applying for electricity connection because it allows the electricity company, Electricité du Liban, locate the construction.

              2- Submit application to EDL and await estimate

              Agency: Electricité du Liban (EDL), Beirut

              The customer submits an application for electricity connection at Electricité du Liban’s offices.

              In addition to the application form, the client needs to submit:

              • copy of the title deed
              • copy of the ID card
              • the original building permit, and
              • electricity bill from the closest building (or meter box number) and its address

               

              3- Receive external inspection by EDL

              Agency: Electricité du Liban (EDL), Beirut

              The application is forwarded to the relevant department at the utility for review. A site inspection is usually carried out to determine the details of the connection.

              The inspector then prepares a report with the specifics of the connection and awaits clearance from the relevant authority at the utility.

              Once clearance is obtained and the inspector has prepared an estimate of the connection fees, the client will need to make the necessary payment at Electricité du Liban’s offices. The client is then given the approved file back along with a “C23” card (with the number of connections and the temporary meter, if needed).

               

              4- Await and receive external works and meter installation from EDL’s service provider

              Agency: Electricité du Liban (EDL), Beirut

              External works start after the client has paid the connection fees. For a connection of 3x200A, if the warehouse is less than 200 meters away from the closest distribution substation, the works will consist of laying out an underground cable from the building to that substation.

              Otherwise, a substation would be needed.

              Any permits needed for the works are obtained by the utility directly.

              The utility picks a contractor to do the external works, and possibly install the meter and turn the electricity on too. The utility however, always supervises the works.

              The contractor is in charge of applying for any required excavation permit with the municipality.

               

              No inspection of the entire internal wiring is done during the process.

               

              5- Obtain final connection from EDL or its contractor

              Agency: Electricité du Liban (EDL), Beirut or its contractor

              Usually it is the utility that turns on electricity, but it all depends on the agreement between the contractor and the utility. The contractor might have the right to also turn on the electricity.

              At times when the utility is overloaded, it normally delegates the works entirely to its contractor that does the works, installs the meter, and turns on the electricity. In this case, the utility only checks the final connection at the end to make sure the installation has been done properly.

              Otherwise, if the agreement with the contractor does not give them this right, meter installation is done by the utility.

              Lorem ipsum dolor sit amet, consectetur adipisicing elit, sed do eiusmod tempor incididunt ut labore et dolore magna aliqua. Ut enim ad minim veniam, quis nostrud exercitation ullamco laboris nisi ut aliquip ex ea commodo consequat. 

              Registering Property in Lebanon

               

              Below is a detailed summary of the steps, involved in registering property in Lebanon. It assumes a standardized case of an entrepreneur who wants to purchase land and a building that is already registered and free of title dispute.

              Procedure                 

              1- Obtain an updated Real Estate Certificate from the Land Registry

              Agency: Land Registry

              Parties obtain an updated Real Estate Certificate from the Land Registry, such certificate mentions the names of the owners, a description of the property and any encumbrance or easment or inscription if any on the property. The Procedure to obtain the Real Estate Certificate is a straight forward one which only requires submission of the request, and the certificate is immediately issued thereafter.

              2- Obtain an official cadastral map

              Agency: Cadastre Administration (Da’irat al Massaha)

              If the area is not specified in the real estate certificate and in the title deed, which is often the case, an official cadastral map and an area certificate must be obtained from the cadastre administration (in Arabic “Dairat al Massaha”).

               

              3          Obtain an urban plan certificate from the Urban Planning Authority and the Municipality

              Agency: Urban Planning Authority and Municipality

              Parties obtain an urban plan certificate from the Urban Planning Authority and the Municipality. This is not strictly required by the law but it is usually requested by the buyer in order to make sure that no special easement or expropriation is planned on the property that he intends to purchase.

               

              4- Obtain tax clearance from the Municipality

              Agency: Municipality

              Obtain clearance from the Municipality to make sure that municipal taxes prior to the sale agreement have been paid. This is not required by law but it is usually requested by the buyer.

              5- Preparation of the sale agreement

              Agency: Notary/attorney

              An attorney or notary public or qualified facilitator prepares the sale agreement in the official form.

              The participation of a lawyer is not mandatory but it is preferred to avoid any mistakes. The sale contract is often drafted by the notary public or by a qualified facilitator.

              However, for complex and delicate real estate transactions where either or both parties need to protect their rights, the contract is usually negotiated and drafted by both parties’ attorneys.

              The Beirut Bar Association on its decision of April 26th, 2012 has set a minimum fee of LBP 2,500,000 for the drafting of a contract. Such minimum fee shall be subject to an increase taking into consideration the contract’s value and importance.

              6- Inspection of the property by the Tax Authority to get an official estimate of its rental value

              Agency: Ministry of Finance

              The Tax Authority at the Ministry of Finance orders an inspection of the property by a controller. This is done to obtain an official estimate of the rental value of the property. A copy of the sale agreement should be submitted to the Ministry of Finance to obtain the official estimate of the rental value.

               

              7- Obtain an official estimate of the rental value of the property from the Tax Authority

              Agency: Ministry of Finance

              An official estimate of the rental value of the property is delivered by the Tax Authority at the Ministry of Finance after the inspection together with a tax discharge (clearance). Sometimes, an occupancy certificate from the Municipality is also requested.

              8- Apply for registration at the Land Registry

              Agency: Land Registry

              The contract, together with the documentation, is presented, either:

              • directly to the Land Registry officer before whom the contract is signed and then the property is registered
              • or to the notary public before whom the contract is signed and then both the contract and the documentation shall be presented to the Land Registry for registration of title.

              If it is presented to the Land Registry, all taxes and duties are paid at the tax authority cashier, which is located at the same building than the Land Registry.

              The taxes and duties to be paid if the contract is presented at the Land Registry are as follows:

              • Proportional stamp duty: 0.3% of contract value.
              • Bar Association tax: 0.1% of contract value.
              • Various taxes, namely:

              – Flat tax on contract: LBP 8,000.

              – Tax (called in Arabic “kaydieh”): LBP 8,000.

              – Flat tax on title deed: LBP 8,000.

              – Tax on new title deed: LBP 50,000

              Total of said flat taxes: LBP 74,000

              – Proportional transfer tax: 5% of contract value or of the value resulting from the official estimate, which is higher.

              – Proportional Municipal tax: 5% of the total amount (i.e. aforementioned 5% transfer tax + L.P. 74,000).

              – Flat stamp duty on new deed: L.P. 5,000

              The Contract is presented to the Assistant Land Registrar, then it will go through one or two officers before it reaches the Land Registrar who would:

              (i)- either accept the contract if he/she agrees on the price that was set by the parties and finds that there are no irregularities in the documents, in which case the contract shall be immediately registered, and thereafter the new deed will be delivered to the buyer.

              (ii)- or refuse to register the contract until the price is amended (i.e. increased) or the irregularities in the documentation is rectified, in which case the Land Registrar’s request shall be satisfied and the contract is to be presented once again for review and acceptance.

              It is only when the Land Registrar approves the signed contract and accepts to record it that the title to property is transferred to the Buyer.

              Then, once the transaction is completed, the new title deed in the name of the Buyer is delivered in about 5-7 business days. As per the express and clear provisions of the law, the buyer acquires full ownership only when the sale contract is recorded (i.e. after its acceptance) in the Land Registry, regardless of when the new deed is delivered to him.

              In case the contract is delivered for signing to the notary public, then both the contract and the documentation shall be presented to the Land Registry for registration of title, in which case the above mentioned costs shall be increased as follows:

              – Notary tax: 0.1% of contract value.

              – Flat tax: LBP 50,000

              – Notary flat tax: LBP 15,000

              – Flat stamp duty on contract: LBP 10,000

              – Tax (called in Arabic “Tahrir wa tanzim”): LBP 34,000

              – Reconstruction tax: LBP 2,500

              – Stamp duty on second copy of contract: LBP 1,000

              – Notary public fees: LBP 200,000

              All taxes and duties are paid directly at the notary public’s office, except for the stamp duty that is paid at the Ministry of Finance if its amount exceeds LBP 200,000

               

              The documentation shall include:

              • Title deed, as proof of ownership (held by seller)
              • Real Estate Certificate (obtained in Procedure 1)
              • Official cadastral map (obtained in Procedure 2)
              • Official estimate of rental value of the property (obtained in Procedure 5)
              • Municipal tax clearance (obtained in Procedure 6)
              • Sale agreement (prepared in Procedure 7)

               

              Trading across Borders in Lebanon

              Export documents

              Bill of lading

              Commercial invoice

              Customs export declaration

              Packing list

              Customs inspection report

              Export documents

              Bill of lading

              Commercial invoice

              Customs export declaration

              Packing list

              Customs inspection report

               

              Labor Market Regulation in Lebanon

              Below is a detailed summary of some of the labor regulations that would apply to local entrepreneurs wishing to hire workers, organize working schedules, improve job quality for workers, or make workers redundant for economic reasons in Lebanon. It measures the regulation of employment, specifically as they affect a local entrepreneur running a supermarket or grocery store operating in the economy’s largest business city (for 11 economies the data are also collected for the second largest business city) and employing 60 employees.

               

              15.0 15.0 15.0 15.0

              No limit but after 24 months worker is treated as indefinite term for purposes of severance pay (Art. 58).Yes Yes No Yes

              Paid annual leave for a worker with 10 years of tenure (working days)Paid annual leave (average for workers with 1, 5 and 10 years of tenure, in working days)No

              Third-party approval if one worker is dismissed? 3rd-party notification if nine workers are dismissed? 3 rd-party approval if nine workers are dismissed?

              Topic Answer
              Fixed-term contracts prohibited for permanent tasks? No
              Maximum length of a single fixed-term contract (months)
              Maximum length of fixed-term contracts, including renewals (months) 24.0
              Minimum wage applicable to the worker assumed in the case study (US$/month) 435.2
              Ratio of minimum wage to value added per worker 0.4
              Working hours
              Maximum number of working days per week 6.0
              Premium for night work (% of hourly pay) 0.0
              Premium for work on weekly rest day (% of hourly pay) 50.0
              Premium for overtime work (% of hourly pay) 50.0
              Restrictions on night work? No
              Whether nonpregnant and nonnursing women can work the same night hours as men Yes
              Restrictions on weekly holiday? No
              Restrictions on overtime work? Yes
              Paid annual leave for a worker with 1 year of tenure (working days)
              Paid annual leave for a worker with 5 years of tenure (working days)
              Redundancy rules
              Maximum length of probationary period (months) 3.0
              Dismissal due to redundancy allowed by law?
              Third-party notification if one worker is dismissed?
              Retraining or reassignment obligation before redundancy? No
              Priority rules for redundancies? Yes
              Priority rules for reemployment? Yes
              Redundancy cost
              Notice period for redundancy dismissal for a worker with 1 year of tenure 4.3
              Notice period for redundancy dismissal for a worker with 5 years of tenure 8.7
              Notice period for redundancy dismissal for a worker with 10 years of tenure 10.7
              Notice period for redundancy dismissal (average for workers with 1, 5 and 10 years of tenure) 7.9
              Severance pay for redundancy dismissal for a worker with 1 year of tenure 0.0
              Severance pay for redundancy dismissal for a worker with 5 years of tenure 7.2
              Severance pay for redundancy dismissal for a worker with 10 years of tenure 14.4
              Severance pay for redundancy dismissal (average for workers with 1, 5 and 10 years of tenure) 7.2
              Job quality
              Equal remuneration for work of equal value? No
              Gender nondiscrimination in hiring? No
              Paid or unpaid maternity leave mandated by law? Yes
              Minimum length of maternity leave (calendar days)? 70.0
              Receive 100% of wages on maternity leave? Yes
              Five fully paid days of sick leave a year? Yes
              Unemployment protection after one year of employment? No
              Minimum contribution period for unemployment protection (months)? n.a.

               

              Toughest Defense Lawyers with Best Results

              Our Attorney

              ME Ralph Eid

              Corporate Lawyer

              Lawyer

              Jean Eid
              Jean Eid
              Founder of Eid Law Firm

              1926 – 1992

              • Born in Btaddine al Loqch – Jezzin – South Lebanon  –  1926.
              • In 1955 he was appointed announcer at Near East Broadcasting Station  – Limassol – Cyprus.
              • In 1957 he was appointed announcer at the Lebanese Ministry of Information
              • In 1958 he was awarded the Lebanese Order of Merit of the rank of Knight during the reign of President Camille Chamoun.
              • holder of a BA in Law from La Sagesse University in 1962
              • Member of Beirut Bar Association – Attorney at Law since 1966 – Subscription number 1948
              • Founder of Eid Law Firm
              • Personal lawyer of the late President Camille Chamoun and a large number of politicians and businessmen
              • He has many intellectual, literary, poetic, cultural and legal articles
              • President of the Association of the old school teachers of Mashmousheh
              • Lecturer, thinker, lawman, the lawyer on appeal
              • Died 1992

              Recent Posts

              Free Legal Advice

              Due To Corona-virus We Are Giving Free Legal Consultations Till Apr 30

              Legal Consultation

              نظرا للظروف الاليمة التي نمر بها جراء انتشار وباء – فيروس كورونا في العالم وفي وطننا الحبيب لبنان. ورغبة منا…

              Offshore Companies in Lebanon

              Offshore Companies in Lebanon The offshore company is a very tempting choice as a business entity/company to choose, With a…

              اختصاص المحاكم اللبنانية للنظر في الطلاق المدني

              في اختصاص المحاكم اللبنانية: نصت المادة 79 أ.م.م على ان تكون المحاكم اللبنانية مختصة بالنظر في المنازعات الناشئة عن عقد…

              working hours

              Monday – Friday: 8:00 – 16:30 Hrs (Phone until 23:30 Hrs)
              Saturday: 8:00 – 13:30 Hrs
              Sunday: Close

              we are here

              Bsalim – Centre Bsalim 394 –  Maten, Lebanon
              Mobile: +961-3442-422